LARE Construction Documentation Flashcards

6 cards from real LARE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 LARE Construction Documentation flashcards as text
  1. A landscape architect is reviewing a submittal from a contractor for a custom-designed steel planter. The submittal includes detailed fabrication drawings, material specifications, and finish samples. What is the primary purpose of the landscape architect's review of these shop drawings?

    Answer: To ensure the proposed planter conforms to the design intent shown in the contract documents.

    The landscape architect's primary responsibility when reviewing shop drawings is to confirm that the contractor's interpretation of the design, as detailed in their drawings, aligns with the original design intent, performance requirements, and aesthetics specified in the construction documents. The review is not for approving means and methods, which are the contractor's responsibility, nor for selecting suppliers or verifying quantities for payment.

  2. During construction of a plaza, the contractor notes a discrepancy. The drawings show a dimension of 10 feet for a seat wall, but the written specifications call for a 12-foot wall. If the contract documents do not contain a specific 'order of precedence' clause, what is the generally accepted principle according to standard AIA documents?

    Answer: The documents are complementary, and the discrepancy should be brought to the landscape architect for clarification.

    Standard AIA General Conditions, such as A201, state that the contract documents are complementary, and what is required by one is as binding as if required by all. There is no automatic hierarchy where one document type governs the other. In the event of a conflict, the contractor must seek clarification from the architect/landscape architect, typically via a Request for Information (RFI), rather than making an assumption.

  3. A landscape architect wants to specify a particular type of permeable paver for a driveway but also wants to allow for competitive bidding. The specification calls for a paver that meets a minimum infiltration rate, a specific compressive strength, and a certain percentage of recycled content, allowing any manufacturer who meets these criteria to be considered. What type of specification is this?

    Answer: Performance

    This is a performance specification because it defines the required results and the criteria by which a product's performance will be verified (e.g., infiltration rate, compressive strength). It does not prescribe a specific manufacturer (proprietary) or a detailed recipe of how the product must be made (prescriptive).

  4. At the conclusion of a project, the contractor provides the landscape architect with a full set of construction drawings marked up with red ink to show all on-site changes, modifications, and final locations of utilities. The landscape architect then incorporates these markups into a clean, final set of electronic drawings. What is this final set of drawings prepared by the landscape architect properly called?

    Answer: Record Drawings

    Record Drawings are the final drawings prepared by the design professional. They incorporate the contractor's on-site changes (which are documented on what are called 'as-built drawings' or markups) into a clean set of official documents reflecting the completed project. As-built drawings are the contractor's markups, not the final version from the architect.

  5. Which of the following documents is prepared by the landscape architect and signed by the owner, contractor, and landscape architect to formally authorize a modification to the contract sum, contract time, or scope of work after the construction contract has been executed?

    Answer: Change Order

    A Change Order is a formal amendment to the construction contract used to document changes affecting the contract sum, time, or scope. It requires agreement and signatures from the owner, contractor, and architect/landscape architect to be valid. An addendum is issued before the contract is signed, an RFI is a question, and an ASI is a minor change not affecting cost or time.

  6. A landscape architect's specifications for soil require the contractor to submit a report from an independent testing laboratory verifying the composition, pH, and organic content of the proposed topsoil mix before it is delivered to the site. This report is part of which formal process?

    Answer: Submittal Process

    The submittal process is the formal procedure during construction administration where the contractor provides information, samples, product data, and reports to the design team for review to ensure that the proposed materials and equipment comply with the contract documents before they are purchased or installed. This soil report is a classic example of a product data submittal.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. clarb.org — Fees, retake fee, test delivery, eligibility, score release, score validity, retake policy, time limit, passing score, registration deadline · verified Oct 2026
LARE Construction Documentation Flashcards — LARE Study Cards with Answers