A KDOT inspector notices that the contractor's quality control testing frequency for hot-mix asphalt is below the required rate. What is the proper documentation action?
-
A
Allow work to continue and note it only in the final project summary
-
B
Record the deficiency in the daily diary with dates, lot numbers affected, and the required versus actual testing frequency, then notify the engineer
-