What is the significance of the 'as-built' plan set that a KDOT inspector helps compile during construction?
-
A
It replaces the contractor's original bid documents
-
B
It records actual field conditions, dimensions, and changes made during construction for long-term asset management and future maintenance
-
C
It is used solely for contractor billing purposes
-
D
It is only required on federally funded projects over $10 million