When a contractor submits a request for information (RFI) on a KDOT project, what is the inspector's primary responsibility?
-
A
Resolve the RFI independently without involving the engineer
-
B
Log the RFI, forward it to the engineer, and track the response timeline
-
C
Reject the RFI if it seems unnecessary
-
D
Answer the RFI verbally to avoid paperwork