According to KDOT practice, what action should be taken when embankment fill material delivered to the project contains significantly more rock than the approved material sample?
-
A
Accept the material if it passes visual inspection
-
B
Reject or quarantine the load and notify the engineer for evaluation
-
C
Increase compaction effort to compensate
-
D
Reduce lift thickness by 50%