When a contractor submits a progress payment estimate, what is the primary document the inspector should verify against?
-
A
The contractor's internal invoice
-
B
The approved bid schedule of values and field measurements
-
C
The project owner's budget spreadsheet
-
D
The subcontractor's billing statement