Which of the following statements BEST describes the relationship between the CSI approach and the Deming Cycle (PDCA)?
-
A
The CSI approach replaces the Deming Cycle in ITIL environments
-
B
The CSI approach and PDCA are parallel frameworks with no direct relationship
-
C
The CSI approach embeds the PDCA cycle as its underlying improvement engine
-
D
PDCA applies only to quality manufacturing, not IT service management