A project manager notices that key stakeholders are disengaged during service transition updates. According to ITIL Practitioner communication principles, what should be the FIRST corrective action?
-
A
Increase the frequency of update emails
-
B
Assess whether the communication medium and content match stakeholder expectations
-
C
Escalate the disengagement to senior management
-
D
Remove disengaged stakeholders from the distribution list