A change request is submitted but lacks sufficient information to assess its risk. According to ISO 20000, what should happen?
-
A
Return it to the requester for clarification
-
B
Classify it as a standard change
-
C
Approve it provisionally and review later
-
D
Escalate it directly to emergency CAB