IKM IT Project Management Principles — Questions and Answers
Question 1: What is the critical path in project management?
- Path with lowest cost
- Longest sequence of dependent tasks determining minimum duration (Correct answer)
- Most important deliverable
- Path requiring most resources
Correct answer: Longest sequence of dependent tasks determining minimum duration
The critical path determines the shortest possible project duration; delays on it delay the project.
Tasks on the critical path have zero float. Tasks off the critical path have float allowing some delay. A project may have multiple critical paths.
Question 2: What is scope creep?
- Reducing scope to meet deadlines
- Uncontrolled expansion of scope without adjusting time or cost (Correct answer)
- Planned scope change
- Moving deliverables to future phases
Correct answer: Uncontrolled expansion of scope without adjusting time or cost
Scope creep is uncontrolled growth through incremental unapproved changes.
Prevention includes clear WBS, formal change control, signed-off requirements, and stakeholder education. Agile mitigates through iterative delivery and regular reprioritization.
Question 3: Which methodology uses time-boxed sprints?
- Waterfall
- PRINCE2
- Scrum (Correct answer)
- Critical Chain
Correct answer: Scrum
Scrum uses fixed-length sprints (2-4 weeks) to deliver product increments.
Scrum defines three roles (Product Owner, Scrum Master, Dev Team), five events (Sprint, Planning, Daily, Review, Retro), and three artifacts (Product/Sprint Backlog, Increment).
Question 4: What is a Work Breakdown Structure (WBS)?
- List of risks
- Hierarchical decomposition of deliverables into work packages (Correct answer)
- Team org chart
- Budget spreadsheet
Correct answer: Hierarchical decomposition of deliverables into work packages
WBS breaks total scope into manageable work packages for planning and estimation.
The 100% rule states WBS must include all project work. Work packages are typically 8-80 hours of effort. WBS forms the basis for schedule, cost, and resource planning.
Question 5: What is earned value management (EVM)?
- Team performance reviews
- Measuring performance by comparing planned work, completed work, and actual costs (Correct answer)
- Software velocity calculation
- Vendor contract management
Correct answer: Measuring performance by comparing planned work, completed work, and actual costs
EVM integrates scope, schedule, and cost data for objective performance measurement.
Key values: PV (planned), EV (earned), AC (actual cost). CPI = EV/AC (>1 under budget). SPI = EV/PV (>1 ahead of schedule). Provides early warning of overruns.
Question 6: What is a project charter?
- Detailed project schedule
- Formal authorization document with initial requirements and stakeholders (Correct answer)
- List of risks
- Task responsibility assignments
Correct answer: Formal authorization document with initial requirements and stakeholders
A charter formally authorizes the project, names the PM, and documents high-level requirements.
Created by the sponsor, it includes business case, objectives, high-level requirements, milestones, budget summary, and stakeholder list. Should be concise and signed.
Question 7: What is a RACI matrix?
- Risk assessment tool
- Defines roles as Responsible, Accountable, Consulted, Informed per task (Correct answer)
- Resource allocation index
- Requirements analysis tool
Correct answer: Defines roles as Responsible, Accountable, Consulted, Informed per task
RACI clarifies roles: Responsible (does work), Accountable (approves), Consulted (input), Informed (updated).
Rules: one Accountable per task, at least one Responsible. Too many R's indicates overload. Too many C's slow decisions. Prevents tasks from falling through cracks.
Question 8: What is the difference between a risk and an issue?
- Risks are more severe
- A risk is potential; an issue is a current problem (Correct answer)
- Issues affect budget; risks affect schedule
- No difference
Correct answer: A risk is potential; an issue is a current problem
A risk is an uncertain future event; an issue is a problem that has materialized.
Risks are managed via risk registers with probability/impact assessments. When a risk materializes, it becomes an issue requiring immediate action.
Question 9: What is the triple constraint?
- People, Process, Technology
- Scope, Time, Cost (Correct answer)
- Quality, Risk, Resources
- Plan, Execute, Monitor
Correct answer: Scope, Time, Cost
The triple constraint shows the interdependent relationship between Scope, Time, and Cost.
Changing one affects the others. If scope increases without extending time, cost must increase. Modern interpretations add quality at the center.
Question 10: Which Agile ceremony focuses on process improvement?
- Sprint Planning
- Daily Standup
- Sprint Review
- Sprint Retrospective (Correct answer)
Correct answer: Sprint Retrospective
The Retrospective is for reflecting on what went well and what to improve.
Common formats include Start/Stop/Continue. The team identifies 1-3 actionable improvements. A psychologically safe environment is essential for honest feedback.
Question 11: What is a project milestone?
- Daily progress report
- Significant point marking key achievements with zero duration (Correct answer)
- Budget threshold
- Risk mitigation strategy
Correct answer: Significant point marking key achievements with zero duration
A milestone marks completion of a major deliverable or phase.
Used in milestone charts for executive reporting, in contracts for payment triggers, and for tracking schedule adherence. Missed milestones trigger escalation.
Question 12: What is the purpose of lessons learned?
- Assign blame for failures
- Document what worked and what did not for future reference (Correct answer)
- Calculate final budget
- Write user manual
Correct answer: Document what worked and what did not for future reference
Lessons learned capture knowledge to improve future project execution.
Should be conducted throughout the project. Output stored in organizational knowledge base. Requires blame-free environment with specific, actionable recommendations.
Question 13: A software project reports a CPI of 0.8 and an SPI of 1.1. What is the project's status?
- Under budget and behind schedule
- Under budget and ahead of schedule
- Over budget and ahead of schedule (Correct answer)
- Over budget and behind schedule
Correct answer: Over budget and ahead of schedule
CPI below 1.0 means cost overrun, while SPI above 1.0 means more work was completed than planned.
Question 14: A one-time hardware delay caused a cost variance that is not expected to recur. Which formula best calculates Estimate at Completion (EAC)?
- EAC = BAC / CPI
- EAC = AC + (BAC - EV) (Correct answer)
- EAC = AC + ETC based on a full re-estimate
- EAC = BAC / (CPI x SPI)
Correct answer: EAC = AC + (BAC - EV)
When a variance is atypical, the remaining work is assumed to proceed at the budgeted rate, so EAC = AC + (BAC - EV).
Question 15: To meet a deadline, a project manager has the testing and coding of independent modules run simultaneously instead of sequentially. Which schedule compression technique is this?
- Fast-tracking (Correct answer)
- Crashing
- Resource leveling
- Resource smoothing
Correct answer: Fast-tracking
Fast-tracking performs activities in parallel that were originally planned in sequence, which usually adds rework risk.
Question 16: An IT project signs a fixed-price contract with a vendor to handle a risky data migration. Which risk response strategy does this represent?
- Avoid
- Mitigate
- Accept
- Transfer (Correct answer)
Correct answer: Transfer
Transferring shifts the financial impact and ownership of a risk to a third party, such as a vendor under a fixed-price contract.
Question 17: What does free float represent for a schedule activity?
- The time an activity can be delayed without delaying the project end date
- The time added between dependent activities to absorb risk
- The time an activity can be delayed without delaying the early start of any successor (Correct answer)
- The difference between the late finish and early start of the project
Correct answer: The time an activity can be delayed without delaying the early start of any successor
Free float measures delay tolerance relative to the immediate successor activities, unlike total float which is relative to the project finish.
Question 18: An IT project team grows from 6 to 10 stakeholders. How many potential communication channels exist with 10 stakeholders?
- 20
- 45 (Correct answer)
- 90
- 100
Correct answer: 45
The formula n(n-1)/2 gives 10 x 9 / 2 = 45 channels.
Question 19: When building a RACI matrix for a system deployment task, which rule is considered best practice?
- Exactly one person should be Accountable for each task (Correct answer)
- Every stakeholder should be marked Consulted on each task
- Each task should have at least two Accountable people for backup
- The Responsible and Accountable roles must always be different people
Correct answer: Exactly one person should be Accountable for each task
Assigning a single Accountable owner prevents confusion about who has final authority and sign-off for the task.