What is the critical path in project management?
Answer: Longest sequence of dependent tasks determining minimum duration
The critical path determines the shortest possible project duration; delays on it delay the project.
What is scope creep?
Answer: Uncontrolled expansion of scope without adjusting time or cost
Scope creep is uncontrolled growth through incremental unapproved changes.
Which methodology uses time-boxed sprints?
Answer: Scrum
Scrum uses fixed-length sprints (2-4 weeks) to deliver product increments.
What is a Work Breakdown Structure (WBS)?
Answer: Hierarchical decomposition of deliverables into work packages
WBS breaks total scope into manageable work packages for planning and estimation.
What is earned value management (EVM)?
Answer: Measuring performance by comparing planned work, completed work, and actual costs
EVM integrates scope, schedule, and cost data for objective performance measurement.
What is a project charter?
Answer: Formal authorization document with initial requirements and stakeholders
A charter formally authorizes the project, names the PM, and documents high-level requirements.
What is a RACI matrix?
Answer: Defines roles as Responsible, Accountable, Consulted, Informed per task
RACI clarifies roles: Responsible (does work), Accountable (approves), Consulted (input), Informed (updated).
What is the difference between a risk and an issue?
Answer: A risk is potential; an issue is a current problem
A risk is an uncertain future event; an issue is a problem that has materialized.
What is the triple constraint?
Answer: Scope, Time, Cost
The triple constraint shows the interdependent relationship between Scope, Time, and Cost.
Which Agile ceremony focuses on process improvement?
Answer: Sprint Retrospective
The Retrospective is for reflecting on what went well and what to improve.
What is a project milestone?
Answer: Significant point marking key achievements with zero duration
A milestone marks completion of a major deliverable or phase.
What is the purpose of lessons learned?
Answer: Document what worked and what did not for future reference
Lessons learned capture knowledge to improve future project execution.
A software project reports a CPI of 0.8 and an SPI of 1.1. What is the project's status?
Answer: Over budget and ahead of schedule
CPI below 1.0 means cost overrun, while SPI above 1.0 means more work was completed than planned.
A one-time hardware delay caused a cost variance that is not expected to recur. Which formula best calculates Estimate at Completion (EAC)?
Answer: EAC = AC + (BAC - EV)
When a variance is atypical, the remaining work is assumed to proceed at the budgeted rate, so EAC = AC + (BAC - EV).
To meet a deadline, a project manager has the testing and coding of independent modules run simultaneously instead of sequentially. Which schedule compression technique is this?
Answer: Fast-tracking
Fast-tracking performs activities in parallel that were originally planned in sequence, which usually adds rework risk.
An IT project signs a fixed-price contract with a vendor to handle a risky data migration. Which risk response strategy does this represent?
Answer: Transfer
Transferring shifts the financial impact and ownership of a risk to a third party, such as a vendor under a fixed-price contract.
What does free float represent for a schedule activity?
Answer: The time an activity can be delayed without delaying the early start of any successor
Free float measures delay tolerance relative to the immediate successor activities, unlike total float which is relative to the project finish.
An IT project team grows from 6 to 10 stakeholders. How many potential communication channels exist with 10 stakeholders?
Answer: 45
The formula n(n-1)/2 gives 10 x 9 / 2 = 45 channels.
When building a RACI matrix for a system deployment task, which rule is considered best practice?
Answer: Exactly one person should be Accountable for each task
Assigning a single Accountable owner prevents confusion about who has final authority and sign-off for the task.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- ikmnet.com — Test delivery, passing score · verified Oct 2026
- online.ikmnet.com — Eligibility, exam format, retake policy, score release, time limit · verified Oct 2026