A project has 4 phases.
Phase 1 takes 3 weeks, Phase 2 takes twice as long as Phase 1, Phase 3 takes half as long as Phase 2, and Phase 4 takes as long as Phase 1 and Phase 3 combined.

How many weeks does the entire project take?

Select your answer