Under FAR 15.406-3, what must a Price Negotiation Memorandum (PNM) document?
-
A
Only the final agreed price and delivery schedule
-
B
The principal elements of the negotiated agreement, including price, technical, and business judgments made
-
C
The contractor's cost proposal in its original form
-
D
The names of all personnel who participated in negotiations