Government Procurement Certification Government Procurement Contract Management & Negotiation 3 — Questions and Answers
Question 1: Under FAR 15.406-3, what must a Price Negotiation Memorandum (PNM) document?
- Only the final agreed price and delivery schedule
- The principal elements of the negotiated agreement, including price, technical, and business judgments made (Correct answer)
- The contractor's cost proposal in its original form
- The names of all personnel who participated in negotiations
Correct answer: The principal elements of the negotiated agreement, including price, technical, and business judgments made
FAR 15.406-3 requires the PNM to document the principal elements of the negotiated agreement, including the judgments made in reaching the agreed price.
Question 2: A contractor requests an equitable adjustment after the government issues a constructive change. What constitutes a 'constructive change'?
- A formal written order to change the contract scope
- Government action or inaction that effectively changes contract requirements without a formal modification (Correct answer)
- A contractor-initiated change to improve performance
- An agreed-upon modification reducing contract price
Correct answer: Government action or inaction that effectively changes contract requirements without a formal modification
A constructive change occurs when government conduct—such as defective specifications or government-caused delays—effectively alters contract requirements without a formal change order.
Question 3: Which termination type allows the government to end a contract when the contractor fails to perform?
- Termination for Convenience (T4C)
- Termination for Default (T4D) (Correct answer)
- Partial Termination
- Termination for Impossibility
Correct answer: Termination for Default (T4D)
Termination for Default (FAR Part 49) allows the government to terminate when a contractor fails to deliver on time, fails to make progress, or fails to perform contract terms.
Question 4: When negotiating a sole-source contract, the contracting officer's price objective must be based on:
- The contractor's proposed price minus 10%
- A fair and reasonable price supported by price or cost analysis (Correct answer)
- The lowest price from a prior competitive acquisition
- The independent government estimate only
Correct answer: A fair and reasonable price supported by price or cost analysis
FAR 15.405 requires the contracting officer to establish a price objective that is fair and reasonable, supported by thorough price or cost analysis techniques.
Question 5: What is the primary distinction between 'price analysis' and 'cost analysis' in source selection?
- Price analysis evaluates profit; cost analysis evaluates overhead
- Price analysis evaluates the offered price without examining underlying costs; cost analysis examines individual cost elements (Correct answer)
- Price analysis is required for all contracts; cost analysis only for cost-reimbursement types
- Price analysis uses historical data; cost analysis uses future projections only
Correct answer: Price analysis evaluates the offered price without examining underlying costs; cost analysis examines individual cost elements
Price analysis (FAR 15.404-1(b)) evaluates the reasonableness of the proposed price without examining cost elements, while cost analysis (FAR 15.404-1(c)) evaluates individual cost components.
Question 6: Under the Truth in Negotiations Act (TINA), certified cost or pricing data must be submitted when the negotiated contract price exceeds what threshold (as of recent updates)?
- $500,000
- $750,000
- $2 million (Correct answer)
- $10 million
Correct answer: $2 million
TINA (now codified at 10 U.S.C. § 3702) requires certified cost or pricing data for negotiated contracts exceeding the current threshold of $2 million.
Question 7: Which of the following is a valid exception to TINA's certified cost or pricing data requirement?
- The contract is for commercial items (Correct answer)
- The contractor has been in business less than three years
- The contract is with a small business concern
- The contract period of performance exceeds five years
Correct answer: The contract is for commercial items
Commercial item acquisitions are explicitly exempt from TINA's certified cost or pricing data requirements because market competition establishes price reasonableness.
Under FAR 15.406-3, what must a Price Negotiation Memorandum (PNM) document?