A growth marketing project is behind schedule. Which approach best describes the 'crashing' technique to recover lost time?
-
A
Remove lower-priority tasks from the project scope
-
B
Add resources to critical path activities to speed them up
-
C
Run tasks in parallel that were originally sequential
-
D
Reduce quality standards to meet the deadline