Site Work and Excavation Flashcards
21 cards from real General Contractor License practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 20 Site Work and Excavation flashcards as text
What is the minimum required distance from the edge of an excavation that spoil piles must be placed to prevent cave-ins?
Answer: 2 feet
OSHA requires spoil piles to be placed at least 2 feet from the edge of an excavation to reduce surcharge loads that could cause collapse.
Which soil classification is considered the most stable for excavation purposes under OSHA standards?
Answer: Type A
Type A soil is the most stable classification, having an unconfined compressive strength of 1.5 tons per square foot or greater.
When performing dewatering operations during excavation, where should the discharge water be directed?
Answer: To a storm drain or approved discharge point away from the site
Discharge water must be directed away from the excavation to an approved point to prevent saturation of the surrounding soil and potential cave-ins.
What must a contractor do before beginning any excavation work in an area with unknown underground utilities?
Answer: Call 811 (Dig Safe) to have utilities located and marked
Federal law requires calling 811 before digging to have underground utilities located and marked, preventing damage and injuries.
A sloped excavation in Type B soil must not exceed a slope ratio of:
Answer: 1H:1V
OSHA requires a maximum slope of 1H:1V (45 degrees) for Type B soils to provide adequate stability.
Which equipment is most appropriate for cutting through rock during excavation when blasting is not permitted?
Answer: Hydraulic hammer (hoe-ram) attachment
A hydraulic hammer or hoe-ram attachment breaks rock mechanically and is used when explosives are not permitted or practical.
What is the purpose of a 'shoring' system in an excavation?
Answer: To support trench walls and prevent cave-ins
Shoring systems use structural members such as hydraulic shores or timber bracing to support trench walls and prevent collapse.
What does the term 'cut and fill' refer to in site grading operations?
Answer: Excavating high areas and using that material to fill low areas to achieve desired grade
Cut and fill balances earthwork by excavating (cutting) elevated areas and using that soil to raise (fill) lower areas, minimizing the need to import or export material.
Which document specifies the required compaction percentage for engineered fill on a construction project?
Answer: Geotechnical (soils) report
The geotechnical or soils report prepared by a licensed engineer specifies required compaction percentages, typically expressed as a percentage of Modified Proctor density.
During excavation, encountering unexpected soft or unstable soil (unsuitable material) at subgrade requires the contractor to:
Answer: Over-excavate and replace with engineered fill or structural aggregate
Unsuitable material must be removed and replaced with approved engineered fill or crushed stone to provide stable bearing capacity for foundations.
What is 'underpinning' as it relates to excavation near existing structures?
Answer: Temporarily or permanently strengthening an existing foundation to support excavation next to it
Underpinning extends or strengthens an existing foundation so that nearby excavation does not undermine its bearing capacity or cause settlement.
What is the primary purpose of installing silt fencing around an excavation site?
Answer: To control sediment runoff and protect adjacent waterways from erosion
Silt fencing is an erosion and sediment control best management practice (BMP) required by stormwater permits to prevent disturbed soil from entering waterways.
A contractor discovers archaeological artifacts while excavating. What is the required immediate action?
Answer: Stop work, secure the area, and notify the appropriate authorities
Federal and state laws (including the National Historic Preservation Act) require stopping work and notifying authorities when suspected archaeological or cultural resources are discovered.
What is 'benching' as an alternative to sloping in trench excavation?
Answer: Cutting the trench wall into a series of horizontal steps or levels
Benching creates a series of horizontal steps in the trench wall to prevent soil from sliding into the excavation, and is allowed in certain soil types per OSHA standards.
Which piece of equipment is best suited for bulk earthmoving operations over long haul distances on a large grading project?
Answer: Scraper (motorized or push-pull)
Self-loading scrapers efficiently cut, carry, and deposit large volumes of soil over longer distances in a single operation, making them ideal for mass grading.
What does 'shrinkage factor' mean in earthwork calculations?
Answer: The reduction in volume when loose soil is compacted relative to its bank volume
Shrinkage factor accounts for the fact that compacted fill occupies less volume than the same material in its natural bank state, affecting fill quantity calculations.
What is 'rock excavation' typically defined as in contract specifications?
Answer: Material that cannot be excavated without blasting or hydraulic breaking due to its hardness
Contract specifications typically define rock excavation as material requiring mechanical breaking (hoe-ram) or blasting to remove, and it is usually paid at a higher unit price.
In an urban excavation project, what is 'sheet piling' primarily used for?
Answer: Creating a watertight vertical barrier to retain soil and groundwater around an excavation
Sheet piling consists of interlocking steel or vinyl sections driven into the ground to retain soil and groundwater, allowing excavation in tight urban spaces without sloping.
What frequency of inspection is required for excavations by a competent person?
Answer: Daily and after any hazardous condition (rain, freeze-thaw, adjacent loads)
OSHA requires a competent person to inspect excavations daily before work begins and as needed throughout the shift, and after rain, freezing, or other events that could affect stability.
What is the OSHA-required maximum depth for an unprotected trench in stable rock?
Answer: Any depth is acceptable in stable rock without protection
OSHA allows vertical walls without protective systems only in stable rock because the rock itself provides the structural support that prevents collapse.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- cslb.ca.gov — Fees, renewal · verified Oct 2026
- web.cslb.ca.gov — Test delivery, exam format, retake policy, score release, score validity · verified Oct 2026
- test-takers.psiexams.com — Exam format, passing score, retake policy, score release, time limit, score validity · verified Oct 2026
- psiexams.com — Eligibility · verified Oct 2026
- www2.myfloridalicense.com — Registration deadline, exam format, passing score, test delivery · verified Oct 2026