  1. A subcontractor falls behind schedule on a critical-path activity. What is the MOST appropriate first step for the general contractor?

    Answer: Issue a formal cure notice and schedule a recovery meeting

    A cure notice formally documents the deficiency and triggers the subcontractor's contractual obligation to recover, while a recovery meeting identifies a corrective action plan.

  2. Which scheduling technique identifies the longest path through a project network and determines the minimum project duration?

    Answer: Critical Path Method (CPM)

    CPM calculates early and late start/finish times for each activity, identifying the sequence of tasks that controls the project's total duration.

  3. A project owner requests a change that adds $45,000 in scope. Before proceeding, the general contractor should:

    Answer: Submit a written change order proposal and wait for written approval

    All scope additions must be documented through a formal change order signed by both parties before work begins to protect payment rights.

  4. What does 'float' (also called slack) represent in a project schedule?

    Answer: The amount of time an activity can be delayed without delaying the project completion

    Float is the scheduling flexibility available on non-critical activities; activities with zero float are on the critical path.

  5. When a project experiences a differing site condition, the contractor is MOST likely entitled to:

    Answer: An equitable adjustment in contract price and/or schedule

    Differing site condition clauses in most public and private contracts entitle the contractor to an equitable adjustment when conditions differ materially from those indicated in the contract documents.

  6. A daily construction log PRIMARILY serves which purpose?

    Answer: Creating a contemporaneous record for dispute resolution and project documentation

    Daily logs document weather, workforce, equipment, visitors, and events, providing contemporaneous evidence critical to resolving future claims or disputes.

  7. Which project delivery method gives the owner a single point of responsibility for both design and construction?

    Answer: Design-Build (DB)

    In Design-Build, one entity holds contracts for both design and construction, creating a single point of accountability for schedule, cost, and quality.

  8. A general contractor notices a design error in the architectural drawings during construction. The BEST course of action is to:

    Answer: Stop all related work and immediately notify the architect and owner in writing

    The contractor must promptly notify the designer and owner in writing to allow for a directed correction, which also protects the contractor from liability for the design defect.

  9. What is the PRIMARY purpose of a pre-construction meeting?

    Answer: Establishing project communication protocols, schedules, and expectations among all parties

    The pre-construction meeting aligns the owner, architect, contractor, and subcontractors on communication channels, submittals, scheduling, and project procedures before work begins.

  10. Liquidated damages (LD) clauses in construction contracts are best described as:

    Answer: A pre-agreed estimate of the owner's damages per day of contractor delay

    Liquidated damages represent a negotiated estimate of actual owner losses per day of delay; courts generally uphold them if the amount was a reasonable pre-estimate, not a penalty.

  11. In project scheduling, a 'milestone' is BEST defined as:

    Answer: A significant event or point in time with zero duration used to mark progress

    Milestones are zero-duration markers representing key project events such as completion of foundations, substantial completion, or permit issuance.

  12. Which document formally transfers ownership risk of materials to the owner before installation?

    Answer: Stored materials payment application with proof of insurance and title

    To request payment for stored materials not yet installed, contractors must provide documentation proving clear title and adequate insurance, transferring risk to the owner.

  13. When managing multiple subcontractors on site simultaneously, the general contractor's scheduling priority should be to:

    Answer: Coordinate trade sequences to minimize conflicts, backcharges, and rework

    Coordinating trade sequencing prevents conflicts such as overhead work above finished floors or MEP rough-in before drywall, reducing costly rework and disputes.

  14. A subcontractor requests a 10-day time extension due to unusually severe weather. The general contractor should:

    Answer: Verify contract weather day allowances and compare against actual historical weather data for the project locale

    Most contracts include a certain number of weather days as the contractor's risk; extensions are only warranted for weather exceeding the contractually assumed baseline, verified against historical data.

  15. A general contractor issues a backcharge to a subcontractor. This typically occurs when:

    Answer: The GC incurs costs to correct, complete, or clean up after a subcontractor's failure

    Backcharges recover costs the GC spent remedying a subcontractor's breach of contract, such as cleanup, rework, or protection of other work.

  16. Which document is used to formally request information or clarification from the architect or engineer during construction?

    Answer: Request for Information (RFI)

    An RFI is the formal mechanism for contractors to ask the design team for clarification on drawings or specifications without assuming the resolution themselves.

  17. What is the 'pay-if-paid' clause in a subcontract, and why is it significant?

    Answer: It conditions the GC's obligation to pay the sub on the GC first receiving payment from the owner, shifting owner nonpayment risk to the sub

    Pay-if-paid clauses transfer the risk of owner nonpayment from the GC to the subcontractor; enforceability varies by state, with some states restricting or prohibiting them.

  18. During project closeout, which of the following should the general contractor compile and deliver to the owner?

    Answer: As-built drawings, warranties, operations and maintenance (O&M) manuals, and final lien waivers

    Complete project closeout documents include as-builts, manufacturer warranties, O&M manuals, training records, and final lien releases to transfer full building responsibility to the owner.

  19. What is retainage in a construction contract, and what is its typical percentage?

    Answer: A portion of each progress payment withheld by the owner (typically 5–10%) until substantial or final completion to ensure contract performance

    Retainage incentivizes contractors to complete all punch list items and protects owners against defective work or incomplete scopes; many states regulate maximum retainage percentages.

  20. A superintendent's PRIMARY responsibility on a construction site is to:

    Answer: Direct and coordinate daily field operations, subcontractors, and workforce to execute the work per plans and schedule

    The superintendent is the on-site manager responsible for daily construction activities, quality control, safety compliance, and coordinating subcontractors to meet project milestones.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. cslb.ca.gov — Fees, renewal · verified Oct 2026
  2. web.cslb.ca.gov — Test delivery, exam format, retake policy, score release, score validity · verified Oct 2026
  3. test-takers.psiexams.com — Exam format, passing score, retake policy, score release, time limit, score validity · verified Oct 2026
  4. psiexams.com — Eligibility · verified Oct 2026
  5. www2.myfloridalicense.com — Registration deadline, exam format, passing score, test delivery · verified Oct 2026