Contracts, Laws, and Agreements Flashcards
6 cards from real General Contractor License practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Contracts, Laws, and Agreements flashcards as text
A general contractor includes a clause in a subcontract stating that the subcontractor will only be paid after the general contractor receives payment from the property owner. If the owner never pays, the contractor is not obligated to pay the subcontractor. What is this type of clause called?
Answer: Pay-If-Paid Clause
A 'Pay-If-Paid' clause makes the owner's payment to the general contractor a condition precedent for the contractor's payment to the subcontractor. This effectively transfers the risk of owner nonpayment from the general contractor to the subcontractor. A 'Pay-When-Paid' clause, by contrast, only governs the timing of the payment, meaning the contractor must still pay the subcontractor within a reasonable time, even if the owner has not paid.
A subcontractor fails to pay a supplier for materials used on a residential project. To secure payment, the supplier files a legal claim against the property itself. This action, which can 'cloud' the property's title and prevent its sale or refinancing until the debt is settled, is known as a:
Answer: Mechanic's Lien
A mechanic's lien is a security interest in the title to property for the benefit of those who have supplied labor or materials that improve the property. It is a common legal remedy for contractors and suppliers who have not been paid for their services, allowing them to place a claim directly on the property.
A dispute arises between a general contractor and a property owner over the quality of finished work on a large commercial project. The contract specifies that disputes will be settled out of court by a neutral third party who will render a binding decision. Which dispute resolution method does this describe?
Answer: Arbitration
Arbitration is a method of dispute resolution where a neutral arbitrator (or a panel of them) hears arguments and evidence from both sides and then makes a decision that is legally binding on the parties. Unlike mediation, which is non-binding and facilitated, arbitration results in a final decision. It is often faster and more private than litigation (going to court).
Which of the following is an example of an implied warranty in a construction contract?
Answer: The assumption that the work will be performed with skill and competence, free from major defects.
An implied warranty is a guarantee that is not explicitly written into the contract but is imposed by law based on the nature of the transaction. The warranty of workmanlike performance, which assumes the work will be done skillfully and without major defects, is a fundamental implied warranty in construction. The other options are all examples of express warranties, which are specifically stated promises.
A general contractor signs a contract that includes a provision requiring them to cover all losses, damages, and legal fees incurred by the property owner, even if a claim arises from the owner's own negligence. This type of provision is best described as a(n):
Answer: Broad Form Indemnification Clause
A broad form indemnification clause requires the indemnitor (the general contractor in this case) to assume liability for all losses, including those caused solely by the negligence of the indemnitee (the property owner). This type of clause provides the maximum possible protection for the indemnitee by shifting all risk to the indemnitor.
In many states, before a construction project begins, a legal document is filed with the county recorder to officially signal the start date of the project. This document protects the owner by defining the start time for mechanic's lien rights and identifying key stakeholders. What is this document called?
Answer: Notice of Commencement
A Notice of Commencement (NOC) is a formal document filed at the beginning of a project that establishes the official start date. It provides key information about the project owner, contractor, and property, and its filing is crucial for establishing the priority of lien rights for all parties involved in the construction process.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- cslb.ca.gov — Fees, renewal · verified Oct 2026
- web.cslb.ca.gov — Test delivery, exam format, retake policy, score release, score validity · verified Oct 2026
- test-takers.psiexams.com — Exam format, passing score, retake policy, score release, time limit, score validity · verified Oct 2026
- psiexams.com — Eligibility · verified Oct 2026
- www2.myfloridalicense.com — Registration deadline, exam format, passing score, test delivery · verified Oct 2026