Which scheduling technique uses probabilistic time estimates (optimistic, most likely, pessimistic) to account for uncertainty?
-
A
Critical Path Method (CPM)
-
B
Program Evaluation and Review Technique (PERT)
-
C
Gantt chart scheduling
-
D
Resource leveling