GCC Cheat Sheet 2026

The 30 highest-yield GCC facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.

125 questions
240 min time limit
70.00% to pass
  1. Which type of cost estimating uses a Work Breakdown Structure (WBS) to aggregate costs from the lowest level upward? Bottom-up estimating
  2. Which document must a general contractor submit to obtain a building permit for a new commercial structure? Construction documents prepared by a licensed design professional
  3. Under OSHA's silica standard for construction (29 CFR 1926.1153), what is the Permissible Exposure Limit (PEL) for respirable crystalline silica? 50 micrograms per cubic meter as an 8-hour TWA
  4. Which ASTM standard classification level requires an estimate accuracy range of -15% to +20%? Class 3
  5. What is the purpose of a Safety Data Sheet (SDS)? To document chemical safety information
  6. Which OSHA standard requires written Lockout/Tagout (LOTO) procedures for construction equipment servicing? 29 CFR 1910.147 (applied to construction through 1926.417)
  7. What is the primary purpose of building codes? To ensure minimum standards for safety, health, and structural integrity
  8. Which fire-resistance rating is typically required for walls separating dwelling units in a Type V-B wood-frame apartment building under the IBC? 1-hour
  9. When a general contractor requires subcontractors to carry a minimum of $1 million per occurrence in general liability coverage, this is an example of: Risk transfer through contractual insurance requirements
  10. Which planning tool breaks project deliverables into progressively smaller components to define the total scope of work? Work Breakdown Structure (WBS)
  11. An existing building undergoing renovation must meet current code for which elements, under most state amendments? Accessibility (ADA), fire protection, and the specific elements being altered
  12. Which estimating method uses historical cost data from similar completed projects to forecast costs for a new project? Analogous estimating
  13. Under OSHA's construction standards, which condition requires a crane operator to immediately cease operations? Sustained wind speed exceeds 30 mph or manufacturer's limit
  14. Which OSHA regulation outlines general safety and health provisions in construction? OSHA 1926 Subpart C
  15. When terminating a subcontractor for default, the general contractor must typically: Provide written notice and a cure period as specified in the subcontract
  16. Which OSHA standard governs personal protective equipment (PPE) selection on construction sites? 29 CFR 1926 Subpart E
  17. Why is a project scope statement important? To define project goals and deliverables
  18. A scaffold collapses injuring three workers. Under OSHA's severe injury reporting rule, the contractor must report the hospitalization within: 24 hours of learning of the hospitalization
  19. A bid bond guarantees that: The contractor will enter into a contract if awarded the bid
  20. What is retainage in construction contracts? Withheld portion of payment until completion
  21. A 'benchmark' shown on a site plan serves what purpose? A reference point of known elevation used to establish all other elevations on site
  22. Which organization publishes the National Electrical Code (NEC) that most US jurisdictions adopt? NFPA (National Fire Protection Association)
  23. Which factor MOST affects the load-bearing capacity of a wood stud wall? Stud spacing, species, grade, and presence of lateral bracing
  24. What is the primary purpose of ASTM E119 in building construction? Establishing standard fire-resistance test methods for building materials
  25. What documentation should accompany quality control activities? Test reports, inspection checklists, non-conformance reports, and corrective actions
  26. Which legal concept requires a contractor to formally notify the owner of a claim within the contract-specified timeframe or risk losing the right to recover? Notice requirement / contractual notice
  27. What does a wire mesh or welded wire fabric (WWF) do when embedded in a concrete slab-on-grade? Controls crack width and holds cracks together if they occur
  28. Which ASHRAE standard sets minimum requirements for ventilation and indoor air quality in commercial buildings? ASHRAE 62.1
  29. A Stormwater Pollution Prevention Plan (SWPPP) must be prepared: Before land disturbance begins
  30. What does a 'nonconformance report' (NCR) formally document on a construction project? Any work or material that deviates from contract requirements
Turn these facts into recall:
Was this helpful?