A contractor is preparing a project schedule and needs to determine which tasks directly impact the project completion date. Which scheduling method identifies the Critical Path?
-
A
Resource-leveling analysis
-
B
Forward and backward pass calculations through the network diagram
-
C
Gantt chart baseline review
-
D
Monte Carlo simulation only