1. The Units Complete technique measures progress by:
Units Complete earns value per completed unit (e.g., installed panels, tested assemblies), making it highly objective and repeatable.
2. Which EVM metric is expressed in currency units rather than as a ratio?
CV = EV - AC is expressed in dollars (or other currency), while CPI, SPI, and TCPI are dimensionless ratios.
3. SPI lower than one indicates that
If the SPI is less than 1, it indicates that the project is behind schedule. This means that the value of the work completed (EV) is less than the planned value (PV), indicating that the project is not progressing as per the scheduled timeline.
4. What is a Planning Package in EVM?
Planning Packages hold budget for future work within a Control Account that has not yet been broken down into detailed work packages.
5. The Contract Budget Base (CBB) equals:
CBB = Negotiated Contract Cost + Authorized Unpriced Work, representing the total authorized budget for the contract.
6. What is the formula for Cost Performance Index (CPI)?
CPI = EV / AC, where a value above 1.0 indicates the project is under budget.