EVM Cheat Sheet 2026

The 30 highest-yield EVM facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.

40 questions
60 min time limit
65.00% to pass
  1. The IEAC (Independent Estimate at Completion) differs from project EAC because it is: Calculated by an independent party or method outside the project team
  2. What are the three categories? Major (High Risk)
  3. The 50/50 earned value technique is most appropriate for: Tasks with duration spanning two reporting periods
  4. At project completion, what value should the cumulative Schedule Variance (SV) always equal, regardless of whether the project finished early or late? Zero
  5. A positive VAC indicates: The project is forecast to finish under the original budget
  6. If a project's cumulative CPI is 0.75 and its TCPI (based on BAC) is 1.35, what does this comparison most strongly suggest? Completing the project within the original budget is highly unlikely
  7. The Percent Schedule Variance (%SV) is expressed as: (SV / PV) × 100
  8. The purpose of the Integrated Baseline Review (IBR) is to: Assess whether the PMB is technically achievable and fully accounts for contract scope
  9. What is the correct formula for Variance at Completion (VAC)? VAC = BAC - EAC
  10. What is the To-Complete Performance Index (TCPI) used for in EVM? To determine the cost efficiency required to meet a budget goal
  11. The Percent VAC is computed as: (VAC / BAC) × 100
  12. What is CPM stand for? Critical Path Method
  13. Fixed Formula techniques in EVM include all of the following EXCEPT: Percent Complete (Subjective Assessment)
  14. Level of Effort (LOE) in EVM is characterized by: Work that cannot be measured by discrete output and earns value based on time passage
  15. Schedule Variance (SV) is calculated as: EV - PV
  16. Which type of earned value technique produces the most objective and auditable performance measurement? Physical Percent Complete supported by measurable criteria
  17. Which EAC formula is most appropriate when both cost and schedule efficiency are expected to influence remaining work? AC + (BAC - EV) / (CPI × SPI)
  18. The Units Complete technique measures progress by: Counting the number of identical physical units completed against the total planned
  19. The Integrated Program Management Report (IPMR) replaced which earlier reporting format? Contract Performance Report (CPR)
  20. The Contract Budget Base (CBB) equals: Negotiated contract cost plus authorized unpriced work
  21. Which earned value technique is most appropriate for Level of Effort work packages? Time-phased budget (earning value based on the passage of schedule time)
  22. CPR/IPMR Format 1 provides: Work Breakdown Structure element performance data by cost and schedule
  23. Rolling Wave Planning in EVM means: Near-term work is planned in detail while future work remains in Planning Packages
  24. At project completion, the SPI always converges to which value? 1.0
  25. The Percent Complete technique requires: A subjective or physical assessment of the fraction of work accomplished
  26. How is SPI calculated? EV/PV
  27. What does PMB stand for in an EVM system? Performance Measurement Baseline
  28. What is the correct formula for Schedule Variance (SV)? SV = EV - PV
  29. A Baseline Change Request (BCR) is required when: Any authorized change to the PMB scope, budget, or schedule is needed
  30. EVMS surveillance by DCMA is conducted to: Verify ongoing compliance with ANSI/EIA-748 guidelines after system acceptance
Turn these facts into recall: