What is the primary purpose of stakeholder engagement in project management?
-
A
To prioritize stakeholder needs over project goals.
-
B
To create long-term partnerships with stakeholders.
-
C
To ensure all stakeholders are kept informed and their concerns addressed
-
D
To reduce the number of stakeholders involved in the project.