In fire protection project scheduling, what does 'float' (also called slack) represent?
-
A
The amount of time a task can be delayed without delaying the project completion
-
B
The buffer added to material delivery timelines
-
C
The extra budget reserved for schedule overruns
-
D
The lag time between sequential inspection activities