A project is 40% complete with actual costs of $600,000 against a planned budget of $500,000 for work performed. What does this indicate for financial forecasting?
Answer: The project has a cost overrun trend that will likely increase the Estimate at Completion above baseline
Spending $600,000 to accomplish $500,000 worth of planned work indicates a cost overrun that, if the trend continues, will result in a total cost higher than the original budget.
What is 'Estimate to Complete' (ETC) in project financial forecasting?
Answer: The expected cost to finish all remaining project work from the current point
ETC is the forecasted cost of completing all work that remains after the current status date, and when added to actual costs gives the Estimate at Completion (EAC).
Which financial planning document shows projected revenues, costs, and net income over the project or product lifecycle?
Answer: Pro forma income statement
A pro forma income statement projects expected revenues and expenses over a future period, helping stakeholders evaluate the financial viability of a project or product.
What is sensitivity analysis in the context of project financial planning?
Answer: A technique that examines how changes in key variables affect financial outcomes
Sensitivity analysis tests how much financial outcomes change when individual input variables (such as labor rates or material costs) vary, helping identify which assumptions most impact the forecast.
A project manager wants to update the financial forecast using Earned Value data. If CPI = 0.80, what does this suggest about the Estimate at Completion?
Answer: EAC will be higher than the original Budget at Completion
A CPI below 1.0 indicates that less value is being earned per dollar spent, so the EAC (often calculated as BAC/CPI) will exceed the original budget.
What is the purpose of a contingency reserve in project financial planning?
Answer: To cover identified risks that may occur during the project
Contingency reserves are set aside within the project budget specifically to address known risks included in the risk register, and are controlled by the project manager.
Which forecasting approach is most appropriate when early project performance data suggests the original cost baseline was flawed?
Answer: EAC = AC + (BAC - EV) / CPI, adjusting remaining work by past performance
When past performance is expected to continue, dividing the remaining budget (BAC - EV) by the CPI adjusts the forecast to reflect the current efficiency rate throughout the rest of the project.