← All Financial Management for Project Managers Flashcard Decks

Cost Estimation and Budgeting Flashcards

6 cards from real Financial Management for Project Managers practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Cost Estimation and Budgeting flashcards as text
  1. Which type of cost estimate is typically prepared during the project initiation phase using analogous techniques and carries an accuracy range of -25% to +75%?

    Answer: Rough Order of Magnitude (ROM) estimate

    A ROM estimate is a high-level approximation made early in a project with limited information, typically ranging from -25% to +75% accuracy.

  2. Bottom-up cost estimating involves:

    Answer: Estimating costs at the work package level and summing them up

    Bottom-up estimating breaks work into the smallest components, estimates each individually, and aggregates them to arrive at the total project cost.

  3. Parametric cost estimating uses:

    Answer: Statistical relationships between historical data and project variables

    Parametric estimating applies a statistical model or cost driver (e.g., cost per square foot) derived from historical data to estimate project costs.

  4. The project cost baseline is best described as:

    Answer: The time-phased budget used to measure and monitor project cost performance

    The cost baseline is the approved, time-phased budget against which actual project costs are tracked and measured throughout execution.

  5. Which cost is directly traceable to a specific project deliverable or work package?

    Answer: Direct cost

    Direct costs can be specifically attributed to a project activity or deliverable, such as labor hours worked on a task or materials purchased for it.

  6. Contingency reserves in project budgeting are set aside to address:

    Answer: Known unknowns — identified risks with uncertain impact

    Contingency reserves cover known risks that have been identified in the risk register but whose exact impact is uncertain.