Financial Management for Project Managers Practice Test
Financial Management for Project Managers Cost Estimation and Budgeting 2
Management reserves in a project budget are intended for:
Select your answer
A
Known risks identified in the risk register
B
Unknown unknowns or unforeseen scope changes
C
Routine administrative project expenses
D
Bonuses and incentives for the project team
Hint