What does a Cost Performance Index (CPI) of 0.85 indicate?
-
A
The project is delivering $1.15 of value for every dollar spent
-
B
The project is 85% complete
-
C
The project is delivering only $0.85 of value for every dollar spent
-
D
The project is 15% ahead of schedule