A negative Cost Variance (CV) of -$75,000 means:
-
A
The project has spent $75,000 more than the value earned
-
B
The project has earned $75,000 more than spent
-
C
The project is behind schedule by $75,000 worth of work
-
D
The project will overrun by exactly $75,000 at completion