What is rubber-baselining in EVM?
-
A
Improperly revising the baseline to hide poor performance without formal authorization
-
B
A valid technique for adjusting baselines after approved scope changes
-
C
Re-baselining after a contract modification
-
D
Shifting budget between Control Accounts with CAM approval