EVM Certification Practice Test
✕
📝 EVM Practice Tests
Best Practices & Methodologies
Communication & Stakeholder Relations
Core Concepts & Fundamentals
Data Analysis & Reporting
Documentation & Record Keeping
Cost Control & Budgeting
Schedule Management & Performance
Forecasting & Estimates at Completion
Industry Regulations & Compliance
Leadership & Team Management
Professional Standards & Ethics
Quality Assurance & Improvement
Risk Management & Assessment
Strategic Planning & Implementation
Technology & Tools
📖 EVM Study Guides
AACE Earned Value Professional (EVP) #1
AACE Earned Value Professional (EVP) — Practice Test 2 #2
AACE Earned Value Professional (EVP)
🎥 EVM Videos
EVM Certification Flashcards
Study Guide
EVM Certification Study Guide
Cheat Sheet
EVM Certification Cheat Sheet
Articles
EVM Certification
EVM Certification Practice Test PDF (Free Printable 2026)
☰
EVM Certification Practice Test
▶
EVM Certification Forecasting & Estimates at Completion 2
Free · Instant Results
What is the TCPI formula when using the original BAC as the cost target?
A
TCPI = (BAC - EV) / (BAC - AC)
B
TCPI = (BAC - AC) / (BAC - EV)
C
TCPI = (EAC - EV) / (EAC - AC)
D
TCPI = EV / BAC