What does the Schedule Variance (SV) measure in Earned Value Management?
-
A
The difference between Earned Value and Planned Value in cost terms
-
B
The number of days the project is behind or ahead of schedule
-
C
The ratio of work completed to work scheduled
-
D
The time remaining to complete all project activities