A facility reports a deviation from its Title V permit emission limit. Under what timeframe must it typically notify the permitting authority?
-
A
Within 24 hours with a written follow-up within 2 days
-
B
Within 48 hours with a written follow-up within 10 days
-
C
Within 2 business days with written follow-up within 30 days
-
D
Within 7 calendar days with a written report within 60 days