Read the first 6 Solution Evaluation and Requirements Lifecycle flashcards as text
  1. A business analyst needs to determine whether a proposed IT system change will negatively affect other related systems. Which activity should they perform?

    Answer: Impact analysis

    Impact analysis evaluates how a proposed change may affect related requirements, systems, processes, and stakeholders across the organization.

  2. Requirements are 'verified' when:

    Answer: They are confirmed to be complete, consistent, correct, and feasible before implementation

    Verification checks requirements quality attributes — ensuring they are clear, complete, and testable — before passing them to implementation.

  3. Which metrics are MOST useful for evaluating solution performance after deployment?

    Answer: Business KPIs tied to the original business objectives

    Business KPIs measure whether the solution is actually achieving the intended business outcomes that justified the investment.

  4. A 'deferred' requirement is one that:

    Answer: Has been approved but scheduled for a future release or iteration

    Deferring a requirement acknowledges its value while postponing implementation to a later phase due to priority, cost, or timeline constraints.

  5. The purpose of a post-implementation review in business analysis is to:

    Answer: Evaluate whether the solution delivered the expected benefits and capture lessons learned

    Post-implementation reviews generate organizational learning by assessing solution performance and identifying improvements for future initiatives.

  6. Change control in requirements management ensures that:

    Answer: All changes to baselined requirements are assessed, approved, and communicated before implementation

    A formal change control process prevents uncontrolled scope changes that can lead to cost overruns, schedule delays, and stakeholder dissatisfaction.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. iiba.org — Renewal, score validity, score release, exam format, passing score, time limit, registration deadline, retake policy, test dates, fees · verified Oct 2026
  2. psiexams.com — Test delivery, eligibility · verified Oct 2026