What is the primary reason phase sequence must be verified before paralleling a generator to a bus for the first time?
-
A
Incorrect phase sequence causes the governor to over-speed the prime mover
-
B
Incorrect phase sequence results in a massive short-circuit current when the breaker closes
-
C
Incorrect phase sequence causes the AVR to lose voltage control
-
D
Incorrect phase sequence prevents the synchroscope from rotating