What is the purpose of a 'block load' test during generator commissioning?
-
A
To test the generator at zero load for 30 minutes
-
B
To apply a large percentage of rated load in a single step to test transient performance
-
C
To run the generator at 50% load indefinitely
-
D
To test only the reactive load capacity