What is the primary purpose of including a 'contingency reserve' in a DP project cost estimate?
-
A
To fund crew bonuses upon successful project completion
-
B
To cover identified risks with uncertain probability or impact that could affect cost
-
C
To pay for planned maintenance already scheduled during the project
-
D
To offset the vessel owner's profit margin