  1. Under Section 404 of the Clean Water Act, which federal agency issues individual permits for discharges of dredged or fill material into waters of the United States?

    Answer: U.S. Army Corps of Engineers

    The U.S. Army Corps of Engineers issues Section 404 permits for discharges of dredged or fill material into waters of the United States.

  2. What is the primary purpose of a Nationwide Permit (NWP) under the Section 404 program?

    Answer: To streamline authorization for activities with minimal adverse environmental effects

    Nationwide Permits are designed to streamline the regulatory process for activities that have minimal individual and cumulative adverse environmental effects.

  3. Which EPA authority under Section 404(c) of the Clean Water Act allows the agency to restrict or prohibit the use of a site for disposal of dredged or fill material?

    Answer: Veto authority

    EPA has veto authority under Section 404(c) to restrict or prohibit use of a disposal site if it determines adverse effects on municipal water supplies, shellfish beds, fisheries, wildlife, or recreational areas would be unacceptable.

  4. A Nationwide Permit 39 (Commercial and Institutional Developments) requires pre-construction notification (PCN) when the activity results in the loss of more than how many acres of waters of the United States?

    Answer: 0.5 acres

    NWP 39 requires a PCN when the activity results in the loss of greater than 0.5 acres of waters of the United States.

  5. Under the Clean Water Act Section 401, which entity must provide water quality certification before a federal permit or license can be issued?

    Answer: The state in which the discharge originates

    Section 401 requires that the state (or authorized tribe) where the discharge originates must certify that the activity complies with state water quality standards before a federal permit is issued.

  6. Which of the following best describes the 'Section 9' permit under the Rivers and Harbors Act of 1899?

    Answer: Authorization for bridges, dams, dikes, or causeways across navigable waters

    Section 9 of the Rivers and Harbors Act requires permits for structures such as bridges, dams, dikes, or causeways that obstruct or alter navigable waters.

  7. What does the term 'minimal effects' mean in the context of qualifying for a Nationwide Permit under the Section 404 program?

    Answer: Both individual and cumulative adverse environmental effects are no more than minimal

    To qualify for a Nationwide Permit, the activity must result in no more than minimal individual and cumulative adverse environmental effects.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. dpor.virginia.gov — Test delivery, exam dates, exam format, passing score, score release, time limit, late registration, exam information · verified Nov 2026
  2. law.lis.virginia.gov — Eligibility, fees, retake policy, score validity · verified Oct 2026