Risk Analysis & Mitigation Strategies Flashcards
7 cards from real CVA practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Risk Analysis & Mitigation Strategies flashcards as text
Which of the following scenarios BEST illustrates a 'secondary risk' introduced by a risk mitigation action?
Answer: A firewall rule blocks an attacker but also disrupts legitimate business traffic
Secondary risks emerge as unintended consequences of control implementation, such as a firewall disrupting business operations while blocking threats.
An analyst is calculating risk using the formula Risk = Threat × Vulnerability × Asset Value. Which scenario reflects the LOWEST risk?
Answer: High threat, low vulnerability, low asset value
With high threat but low vulnerability and low asset value, the multiplicative result is significantly reduced compared to combinations with high values across all three factors.
A risk analyst identifies a new zero-day vulnerability with no available patch. Which mitigation strategy is MOST appropriate in the short term?
Answer: Implement compensating controls such as network segmentation and enhanced monitoring
When no patch exists, compensating controls like segmentation and monitoring reduce exposure and detect exploitation attempts until a patch is available.
Which of the following BEST describes the relationship between a threat, a vulnerability, and an exploit in risk analysis?
Answer: A threat is a potential harm source; a vulnerability is a weakness; an exploit is the mechanism used to leverage the weakness
In risk analysis, threats are potential harm sources, vulnerabilities are weaknesses, and exploits are the specific techniques that turn vulnerabilities into realized threats.
An organization wants to measure the effectiveness of its risk mitigation controls over time. Which metric is MOST useful?
Answer: Reduction in residual risk after control implementation
Tracking the reduction in residual risk directly measures whether implemented controls are achieving the intended decrease in exposure.
During risk prioritization, an analyst uses a 5×5 risk matrix. A risk rated 4 (likelihood) × 5 (impact) should be compared to a risk rated 5 × 4. What is TRUE about these two risks?
Answer: They are equal in aggregate risk score but may warrant different responses
Both risks produce a score of 20, so their aggregate risk is equal, but treatment strategies may differ based on whether managing likelihood or impact is more feasible.
Which phase of the risk management lifecycle involves continuously monitoring the risk environment to identify changes that could affect the risk profile?
Answer: Risk monitoring and review
Risk monitoring and review is the ongoing phase that detects new risks, evaluates control effectiveness, and updates the risk register as conditions change.
How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- mile2.com — Test delivery, eligibility, retake policy, score validity, passing score, fees · verified Oct 2026