What action should an inspector take if a nuclear gauge reading shows compaction below the required density?
-
A
Allow the contractor to proceed and re-test at the end of the day
-
B
Reject the lift and require the contractor to re-compact and retest
-
C
Average the result with the previous passing test
-
D
Increase the required density threshold by 2%