Technical Project Delivery Flashcards
7 cards from real CTP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Technical Project Delivery flashcards as text
In Scrum, who is responsible for maximizing product value and ordering the product backlog?
Answer: Product Owner
The Product Owner owns the product backlog and decides the order of items to maximize value.
A team completed 30, 34, and 26 story points over its last three sprints. What is a reasonable velocity for planning the next sprint?
Answer: 30 points
Averaging recent sprints (90 / 3 = 30 points) gives a realistic velocity for planning.
What is the main purpose of a sprint retrospective?
Answer: Inspect the team's process and agree on improvements
The retrospective focuses on how the team worked and what to improve in the next sprint.
In a Kanban system, what is the main reason for setting work-in-progress (WIP) limits?
Answer: To expose bottlenecks and improve flow
WIP limits stop overloading, expose bottlenecks, and shorten cycle time.
A burndown chart shows the remaining-work line flat for several days mid-sprint. What is the most likely meaning?
Answer: Work is not being completed or scope was added
A flat burndown line means remaining work is not going down, often due to blockers or added scope.
What does the 'Definition of Done' provide to an agile team?
Answer: A shared standard of quality an increment must meet to be complete
The Definition of Done is a shared checklist of quality criteria that applies to every increment.
Which approach is best suited for a project with stable, well-understood requirements and strict regulatory documentation needs?
Answer: Predictive (waterfall)
Predictive approaches suit fixed requirements and heavy upfront documentation and approval needs.