Technical Project Delivery Flashcards
7 cards from real CTP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Technical Project Delivery flashcards as text
A project has a planned value of $50,000, earned value of $40,000, and actual cost of $45,000. What is the schedule performance index (SPI)?
Answer: 0.80
SPI equals EV divided by PV, so $40,000 / $50,000 = 0.80, meaning the project is behind schedule.
Using the same figures (EV $40,000, AC $45,000), what is the cost variance?
Answer: -$5,000
Cost variance equals EV minus AC, so $40,000 - $45,000 = -$5,000, which shows a cost overrun.
If budget at completion is $200,000 and CPI is 0.80, what is the estimate at completion assuming current performance continues?
Answer: $250,000
EAC equals BAC divided by CPI, so $200,000 / 0.80 = $250,000.
What does a to-complete performance index (TCPI) greater than 1.0 indicate?
Answer: The remaining work must be done more efficiently than planned to meet the target
A TCPI above 1.0 means the team must achieve better cost efficiency on remaining work to hit the budget target.
Which reserve is set aside for identified risks and is usually controlled by the project manager?
Answer: Contingency reserve
Contingency reserves cover known risks and are part of the cost baseline.
A vendor contract pays actual costs plus a fixed fee regardless of performance. Which contract type is this?
Answer: Cost plus fixed fee
Cost plus fixed fee reimburses allowable costs and adds a set fee that does not change with performance.
Which contract type places the most cost risk on the seller?
Answer: Firm fixed price
Under a firm fixed price contract the seller absorbs any cost overruns.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. We have not yet matched this exam's facts to an official source, so confirm fees, dates and rules with the exam body. Editorial policy