Technical Project Delivery Flashcards
7 cards from real CTP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Technical Project Delivery flashcards as text
A task has an early start of day 5, early finish of day 9, late start of day 8, and late finish of day 12. What is its total float?
Answer: 3 days
Total float equals late start minus early start (8 - 5) or late finish minus early finish (12 - 9), which is 3 days.
Which dependency type means Task B cannot finish until Task A finishes?
Answer: Finish-to-finish
A finish-to-finish dependency ties the completion of the successor to the completion of the predecessor.
A project manager adds extra resources to critical path tasks to shorten the schedule, which raises cost. What technique is this?
Answer: Crashing
Crashing shortens duration by adding resources to critical path activities, usually at extra cost.
Which schedule compression technique carries the greatest risk of rework?
Answer: Fast tracking
Fast tracking runs tasks in parallel that were meant to run in sequence, which increases the chance of rework.
What is the lowest level of a work breakdown structure called?
Answer: Work package
The work package is the lowest WBS level, where cost and duration can be estimated and managed.
A team uses a three-point estimate with optimistic 4, most likely 6, and pessimistic 14 days. What is the PERT (beta) estimate?
Answer: 7 days
PERT uses (O + 4M + P) / 6, so (4 + 24 + 14) / 6 = 7 days.
Which document records the agreed-upon scope, WBS, and WBS dictionary used to measure scope performance?
Answer: Scope baseline
The scope baseline consists of the approved scope statement, WBS, and WBS dictionary.