โ† All CTP Flashcard Decks

Technical Project Delivery Flashcards

7 cards from real CTP practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Technical Project Delivery flashcards as text
  1. A task has an early start of day 5, early finish of day 9, late start of day 8, and late finish of day 12. What is its total float?

    Answer: 3 days

    Total float equals late start minus early start (8 - 5) or late finish minus early finish (12 - 9), which is 3 days.

  2. Which dependency type means Task B cannot finish until Task A finishes?

    Answer: Finish-to-finish

    A finish-to-finish dependency ties the completion of the successor to the completion of the predecessor.

  3. A project manager adds extra resources to critical path tasks to shorten the schedule, which raises cost. What technique is this?

    Answer: Crashing

    Crashing shortens duration by adding resources to critical path activities, usually at extra cost.

  4. Which schedule compression technique carries the greatest risk of rework?

    Answer: Fast tracking

    Fast tracking runs tasks in parallel that were meant to run in sequence, which increases the chance of rework.

  5. What is the lowest level of a work breakdown structure called?

    Answer: Work package

    The work package is the lowest WBS level, where cost and duration can be estimated and managed.

  6. A team uses a three-point estimate with optimistic 4, most likely 6, and pessimistic 14 days. What is the PERT (beta) estimate?

    Answer: 7 days

    PERT uses (O + 4M + P) / 6, so (4 + 24 + 14) / 6 = 7 days.

  7. Which document records the agreed-upon scope, WBS, and WBS dictionary used to measure scope performance?

    Answer: Scope baseline

    The scope baseline consists of the approved scope statement, WBS, and WBS dictionary.

Written and edited by , founder of Practice Test Geeks, with AI assistance. We have not yet matched this exam's facts to an official source, so confirm fees, dates and rules with the exam body. Editorial policy