Project Management & Execution Flashcards
7 cards from real CTP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Management & Execution flashcards as text
A project has a Budget at Completion of $200,000 and a CPI of 0.8. Assuming current performance continues, what is the Estimate at Completion?
Answer: $250,000
EAC = BAC ÷ CPI = 200,000 ÷ 0.8 = $250,000.
Which activity is the primary purpose of a lessons-learned session at project close?
Answer: Capturing what worked and what did not for future projects
Lessons learned document knowledge to improve future projects and become organizational process assets.
In Kanban, what is the main purpose of setting work-in-progress (WIP) limits?
Answer: To improve flow and expose bottlenecks
WIP limits keep teams from overloading stages, which improves flow and highlights constraints.
A sprint burndown chart that stays flat for several days most likely indicates what?
Answer: Work is not being completed or remaining work is not being updated
A flat burndown shows remaining work is not decreasing, which signals blocked tasks or stale updates.
A risk with a 30% probability and a $50,000 impact has what expected monetary value (EMV)?
Answer: $15,000
EMV = probability × impact = 0.30 × $50,000 = $15,000.
Which type of contract places the most cost risk on the seller?
Answer: Firm fixed price
In a firm fixed-price contract the seller must absorb any cost overruns.
What does the 'triple constraint' in project management refer to?
Answer: Scope, time, and cost
The triple constraint holds that changing scope, time, or cost affects the others and overall quality.