Using PERT, an activity has an optimistic estimate of 4 days, most likely of 6 days, and pessimistic of 14 days. What is the expected duration?
Answer: 7 days
PERT expected time = (O + 4M + P) ÷ 6 = (4 + 24 + 14) ÷ 6 = 7 days.
A team member requests adding a new feature mid-project. Under formal change control, what should happen first?
Answer: Submit a change request for impact analysis
Changes must go through a documented change request so impact on scope, cost, and schedule can be evaluated.
Uncontrolled expansion of project scope without adjustments to time, cost, or resources is called what?
Answer: Scope creep
Scope creep is unapproved, gradual growth in scope that is not matched by resource or schedule changes.
The lowest level of a work breakdown structure, where cost and duration can be reliably estimated, is called a what?
Answer: Work package
Work packages are the lowest WBS level and the basis for estimating, scheduling, and assigning work.
Which risk response strategy shifts the impact of a threat to a third party, such as through insurance or a fixed-price contract?
Answer: Transfer
Transferring a risk moves its financial impact and ownership to another party without eliminating it.
A project has a Planned Value of $60,000 and an Earned Value of $45,000. What does the Schedule Variance indicate?
Answer: The project is $15,000 behind schedule
SV = EV − PV = −$15,000, so less work has been completed than planned.
In Scrum, who is responsible for maximizing product value and prioritizing the product backlog?
Answer: Product Owner
The Product Owner owns and orders the product backlog to maximize value delivered.