  1. A task has an early start of day 5, early finish of day 9, late start of day 8, and late finish of day 12. What is its total float?

    Answer: 3 days

    Total float equals late start minus early start (8 − 5 = 3 days).

  2. Which dependency type is most common in network diagrams, where Task B cannot start until Task A is complete?

    Answer: Finish-to-Start

    Finish-to-Start is the default and most widely used precedence relationship.

  3. A project's Earned Value is $40,000 and its Actual Cost is $50,000. What is the Cost Performance Index (CPI)?

    Answer: 0.80

    CPI = EV ÷ AC = 40,000 ÷ 50,000 = 0.80, meaning the project is over budget.

  4. Adding more resources to critical path tasks to shorten the schedule, usually at increased cost, is called what?

    Answer: Crashing

    Crashing compresses the schedule by adding resources to critical activities, typically raising cost.

  5. Performing activities in parallel that were originally planned in sequence is known as what?

    Answer: Fast tracking

    Fast tracking overlaps sequential activities, which saves time but increases rework risk.

  6. Which document formally authorizes a project and gives the project manager authority to use organizational resources?

    Answer: Project charter

    The project charter, issued by the sponsor, formally authorizes the project and the PM's authority.

  7. In a RACI matrix, how many people should normally be 'Accountable' for a single task?

    Answer: Exactly one

    RACI best practice assigns exactly one Accountable person per task to avoid confusion over ownership.