During a test, a technician observes an unexpected voltage spike exceeding the test article's rated limit. What is the FIRST action the test conductor should take?
-
A
Document the spike in the test log
-
B
Immediately initiate an emergency shutdown
-
C
Notify the project engineer for guidance
-
D
Reduce power incrementally to safe levels