A Scrum Team wants to use a Cumulative Flow Diagram (CFD). What does a widening band in a specific workflow state indicate?
-
A
Work is flowing smoothly through that state
-
B
A bottleneck or accumulation of work is building up in that state
-
C
The team is completing more items than planned
-
D
Story point estimates are increasing over time