In a precedence diagramming method (PDM) schedule, a finish-to-start relationship with a lag of 5 days means:
-
A
The successor starts 5 days before the predecessor finishes
-
B
The successor cannot start until 5 days after the predecessor finishes
-
C
The predecessor and successor must overlap by 5 days
-
D
The successor finishes 5 days before the predecessor